Key takeaways
- If two quotes are hard to compare, the RFQ was incomplete; fix the brief before negotiating price.
- Score missing line items as a cost, not as a discount.
- An equivalent product needs supporting data, not just a catalog label.
- Freight, packaging, voltage and documentation often explain more of the spread than the pump itself.
The RFQ guide explains how to prepare the inquiry. Quote comparison starts after every bidder has the same drawings and equipment package checklist. If the issue sets differ, correct that before comparing totals.
Start with a compliance pass
Read each quotation once without looking at the total. Map every priced line to the requested schedule and mark it included, excluded, substituted or unanswered. Keep an exception log with the bidder’s wording and the clarification needed.
A short quotation may be pricing only major products. A longer quotation may include valves, freight, documentation or commissioning. The compliance pass separates those scope differences before price influences the review.
Compact comparison table
Use one column per bidder and one row per comparison item, as in the table. The first row is a filled example. It is not a real offer and it has no price. Copy the blank rows underneath it.
Scroll horizontally to see all columns when the table extends beyond the screen.
If a blank cell is still empty, that quotation is not finished. Deliverable: a completed sheet in which every price cell points at a schedule line, and the example row is not treated as a bid.
Add a document reference beside each answer. A check mark without a page, schedule line or attached data sheet is hard to verify later.
Normalize scope without hiding uncertainty
Create an adjustment sheet for every item that is missing or treated differently:
Scroll horizontally to see all columns when the table extends beyond the screen.
Keep allowances visible. Do not insert a guessed number into the total and then present the normalized price as certain. The purpose is to show why offers differ and which questions can change the ranking.
Where quotations usually diverge
- Scope: one bidder prices a pump and filter; another prices the loop. Use the drawings and BOM checklist as the scorecard.
- Equivalents: a substitute pump that cannot hit the design point is not equivalent.
- Climate hardware: hot, dusty projects need the unglamorous extras listed in equipment for hot climates.
- Cover systems: compare covers only as complete component sets, not as fabric-only lines.
- Import assumptions: duties, packing and voltage belong in the quote if the goods cross a border; see the importing checklist.
Review technical equivalents
For a substituted pump, compare the offered curve at the requested flow and head. For a filter, compare area, flow range and service clearance. For a heater or treatment item, compare the project input stated in the RFQ with the offered data sheet. A familiar brand name is not evidence that two models are interchangeable.
Check interfaces too. Connection sizes, controls, electrical supply and physical clearances can change builder work even when the main performance value is acceptable. Record the review decision and the data sheet revision used to make it.
If the technical reviewer needs more information, keep the item open. Do not approve it because the commercial deadline arrived first.
Score the parts that affect delivery
Use a simple scoring sheet that reflects the project. Price can be one column, with separate columns for scope completeness, technical compliance, delivery assumptions, documentation and stated support. Write the scoring rule before opening the final commercial totals if the procurement process requires that separation.
A score should point back to evidence. For example, documentation gets credit when the requested manuals and data sheets are attached, not when the quotation promises to send them later.
Keep commercial and technical comments separate. The technical reviewer should not have to decide freight terms, and the buyer should not approve a pump curve without the design point.
What to request before you decide
A line-item response on your RFQ template, data sheets for every substitution, and a written exclusion list. Related buyer-side pages sit in the Procurement & Specifications hub.
Before award, issue one final clarification record and ask the bidder to confirm it. Attach the accepted schedule, data sheets, exclusions, delivery terms and warranty to the order. This prevents a clean comparison sheet from being replaced by a shorter purchase order that loses the conditions used for the decision.
Frequently asked questions
How many quotations should I collect?
This guide's general suggestion is three complete quotations on one schedule, and only when those quotations are genuinely competitive. A buyer's own procurement rules can require a different number. For U.S. federal simplified acquisitions, FAR 13.106-1(a) tells the contracting officer to consider FAR 13.104 before requesting quotations. FAR 13.104(b) says that, when synopsis is not required and the notice is not provided through the Governmentwide point of entry, consider soliciting at least three sources. That instruction applies inside the Federal Acquisition Regulation. It does not set a rule for private buyers or for purchases outside that system.
Should I pick the cheapest complete offer?
Not automatically. Weight documentation quality, spare-parts pricing, lead time and whether the components work as one system. The cheapest complete offer can still be the wrong hydraulic match.
Sources
- Pool Pumps — ENERGY STAR Accessed August 23, 2026.
- Model Aquatic Health Code — U.S. Centers for Disease Control and Prevention Accessed August 23, 2026.
- FAR 13.106-1, Soliciting competition (eCFR text current as of 7 October 2026) — U.S. eCFR Accessed October 11, 2026.
- FAR 13.104, Promoting competition (eCFR text current as of 7 October 2026) — U.S. eCFR Accessed October 11, 2026.